Tangy Repower

In 2019, SSE Renewables was granted consent by Scottish Ministers to construct and operate Tangy IV (Tangy Repower), a 16 turbine wind farm with turbines up to 149.9 metres in height. The project would replace the existing 22 turbine Tangy Wind Farm, located approximately 9km northwest of Campbeltown on the west coast of the Kintyre Peninsula in Argyll & Bute.
However, the project which received consent is no longer deliverable in its current form, for two related reasons. First, turbines of the consented blade tip height of 149.9m are effectively no longer available on the market. The onshore wind turbine market has moved towards larger, more efficient machines, and manufacturers are increasingly phasing out turbines of the smaller dimensions consented in 2019. A variation to increase the consented tip height is therefore needed to enable a turbine that is available to be procured and installed. Second, the consented scheme is no longer commercially viable in its current form, principally due to rising supply chain costs and high transmission charges affecting the onshore wind sector in Scotland. The taller, more efficient turbines proposed both restore the commercial viability of the project and allow a currently available turbine model to be procured.
To raise awareness of the application and provide details of where hard copies can be viewed etc., a Public Notice was placed in local and national newspapers. A copy of the notice is shared below:-
Section 36C Variation Application
Thank you to everyone who attended our public exhibitions in August 2025 and March 2026. It was great to meet local residents and interested parties, discuss our plans, and answer questions.
Feedback from these events, alongside input from statutory consultees, environmental surveys and technical assessments, has helped inform our Section 36C Variation Application to the Energy Consents Unit.
You can view all the Application documents in the links below. Links for the 2018 consented application (Tangy IV S36) are also below should you wish to re-visit them.
Decommissioning Tangy
The existing Tangy Wind Farm consists of two developments (Tangy I and Tangy II) with a combined installed capacity of 18.7MW. Tangy I comprises 15 turbines, and Tangy II comprises 7 turbines.
If consent is granted for the variation to Tangy Repower, the existing 22 turbines — some of which have been operating since 2003 — will be removed and replaced with 16 modern, more efficient turbines. Advances in turbine design mean the site could generate significantly more electricity, with a potential increase in capacity from 18.7MW to up to 96MW.
We have applied to Argyll and Bute Council, in July 2026, seeking approval for an extension to the operational life of Tangy I and Tangy II wind farms until 2032. If approved this will enable the existing wind farms to continue operating while Scottish Ministers consider our application to vary the S.36 consent for the repowering of the Tangy IV Wind Farm.
Important documents
Tangy IV S36C Variation
- S36C Cover Letter - Tangy IV Wind Farm S36C Application
- S36C Cover Letter - Tangy IV Wind Farm S36C Application - Appendix 1 - Decision Letter
- S36C Cover Letter - Tangy IV Wind Farm S36C Application - Appendix 2 - Draft Variations to Annex 1 and 2
- S36C Cover Letter - Tangy IV Wind Farm S36C Application - Appendix 3 - Figure 1.3 Proposed Varied Development Layout
- S36C Cover Letter - Tangy IV Wind Farm S36C Application - Appendix 4 - Public Notice
- S36C Cover Letter - Tangy IV Wind Farm S36C Application - Appendix 5 - MD Checklist
- Volume 1 - Cover Page
- Volume 1 - Contents Page
- Vol 1 - Glossary and Abbreviations
- Vol 1 - Non-Technical Summary
- Vol 1 - NTS Figure 1.1 - Site Location
- Vol 1 - NTS Figure 1.2 - Environmental Constraints
- Vol 1 - NTS Figure 1.3 - Proposed Varied Development Layout
- Vol 1 - NTS Figure 1.4 - Consented And Proposed Varied Layouts
- Voume 2 - Cover Page
- Volume 2 - Contents Page
- Vol 2 - Preface
- Vol 2 - Chapter 1 - Introduction
- Vol 2 - Chapter 2 - Design Iteration and Description of Proposed Varied Development
- Vol 2 - Chapter 3 - Approach to EIA
- Vol 2 - Chapter 4 - Planning and Renewable Energy Policy Context
- Vol 2 - Chapter 5 - Landscape and Visual
- Vol 2 - Chapter 6 - Ornithology
- Vol 2 - Chapter 7 - Ecology and Nature Conservation
- Vol 2 - Chapter 8 - Geology, Soils and Peat
- Vol 2 - Chapter 9 - Surface Water
- Vol 2 - Chapter 10 - Cultural Heritage
- Vol 2 - Chapter 11 - Noise
- Vol 2 - Chapter 12 - Access Traffic and Transport
- Vol 2 - Chapter 13 - Land Use, Socio-Economics and Recreation
- Vol 2 - Chapter 14 - Shadow Flicker
- Vol 2 - Chapter 15 - Aviation
- Vol 2 - Chapter 16 - Summary of Impacts and Schedule of Mitigation
Chapter 1 Intro
- Vol 3a - Figure 1.1 - Site Location
- Vol 3a - Figure 1.2 - Proposed Varied Development Layout and Operational Development
- Vol 3a - Figure 1.3 - Proposed Varied Development Layout
- Vol 3a - Figure 1.4 - Consented And Proposed Varied Layouts
Chapter 2 Design iteration and description of development
- Vol 3a - Figure 2.1 Indicative Turbine Geometry
- Vol 3a - Figure 2.2 Indicative WTG Foundation
- Vol 3a - Figure 2.3 Indicative Access Track Details
- Vol 3a - Figure 2.4 Typical Crane Hardstanding
- Vol 3a - Figure 2.5 Indicative Mast Elevations
- Vol 3a - Figure 2.6 Construction Compound - Indicative Layout
- Vol 3a - Figure 2.7a Indicative Substation Plan
- Vol 3a - Figure 2.7b Indicative Substation Elevations
- Vol 3a - Figure 2.8 Indicative LiDAR
- Vol 3a - Figure 2.9 - Consented Development
- Vol 3a - Figure 2.10 - Scoping Layout
- Vol 3a - Figure 2.11 - Proposed Varied Development
- Vol 3a - Figure 2.12a - T01 Infrastructure Design Review
- Vol 3a - Figure 2.12b - T02 Infrastructure Design Review
- Vol 3a - Figure 2.12c - T03 Infrastructure Design Review
- Vol 3a - Figure 2.12d - T04 Infrastructure Design Review
- Vol 3a - Figure 2.12e - T05 Infrastructure Design Review
- Vol 3a - Figure 2.12f - T06 Infrastructure Design Review
- Vol 3a - Figure 2.12g - T07 Infrastructure Design Review
- Vol 3a - Figure 2.12h - T08 Infrastructure Design Review
- Vol 3a - Figure 2.12i - T09 Infrastructure Design Review
- Vol 3a - Figure 2.12j - T10 Infrastructure Design Review
- Vol 3a - Figure 2.12k - T11 Infrastructure Design Review
- Vol 3a - Figure 2.12l - T12 Infrastructure Design Review
- Vol 3a - Figure 2.12m - T13 Infrastructure Design Review
- Vol 3a - Figure 2.12n - T14 Infrastructure Design Review
- Vol 3a - Figure 2.12o - T15 Infrastructure Design Review
- Vol 3a - Figure 2.12p - T16 Infrastructure Design Review
Chapter 5 LVIA - High Res
- Vol 3a - Figure 5.1 - Study Area with ZTV (A3)
- Vol 3a - Figure 5.2 - Study Area with ZTV (A1)
- Vol 3a - Figure 5.3 - Comparative ZTV of Consented Development and PVD
- Vol 3a - Figure 5.4 - Designated and Protected Landscapes
- Vol 3a - Figure 5.5 - Landscape Character Types in Detailed Study Area
- Vol 3a - Figure 5.6 - Viewpoints (A3)
- Vol 3a - Figure 5.7 - Viewpoints (A1)
- Vol 3a - Figure 5.8 - Visual Receptors
- Vol 3a - Figure 5.9 - Cumulative Sites Within 60km
- Vol 3a - Figure 5.10 - Cumulative Sites Included in the Assessment
- Vol 3a - Figure 5.11 - Cumulative ZTV - Proposed Varied Development with All CZTV Sites
- Vol 3a - Figure 5.12 - Cumulative ZTV - Proposed Varied Development with All Operational Sites
- Vol 3a - Figure 5.13 - Cumulative ZTV - PVD with All Operational and Consented Sites
- Vol 3a - Figure 5.14 - Cumulative ZTV PVD with Beinn an Tuirc (Phase 3) and Cnoc Buidhe
- Vol 3a - Figure 5.15 - Cumulative ZTV - PVD with Beinn an Tuirc 1 and Beinn an Tuirc 2
- Vol 3a - Figure 5.16 - Cumulative ZTV - PVD with Auchadaduie and Blary Hill
- Vol 3a - Figure 5.17 - Cumulative ZTV - PVD with Allt Domhain and West Torrisdale
- Vol 3a - Figure 5.18 - Cumulative ZTV - PVD with Clachaig Glen and Killean
- Vol 3a - Figure 5.19 - Cumulative ZTV - PVD with Deucheran Hill and Gigha and Extension
- Vol 3a - Figure 5.20 - Cumulative ZTV - PVD with Cour and High Constellation
- Vol 3a - Figure 5.21 - Cumulative ZTV - PVD with Breackerie and Freasdail
Chapter 6 Figures - Ornithology
- Vol 3a - Figure 6.1 - Vantage point
- Vol 3a - Figure 6.2 - Goose vantage point
- Vol 3a - Figure 6.3 - Wildfowl flights
- Vol 3a - Figure 6.4 - Wildfowl non breeding flights
- Vol 3a - Figure 6.5 - GWG non breeding flights
- Vol 3a - Figure 6.6 - Wader breeding flights
- Vol 3a - Figure 6.7 - Wader non breeding flights
- Vol 3a - Figure 6.8 - Common gull breeding flights
- Vol 3a - Figure 6.9 - Gull breeding flights
- Vol 3a - Figure 6.10 - Gull non-breeding flights
- Vol 3a - Figure 6.11 - Raptor breeding flights
- Vol 3a - Figure 6.12 - Raptor non breeding
- Vol 3a - Figure 6.13 - Common gull flights Spring 2026
- Vol 3a - Figure 6.14 - Gull flights excl. CM Spring 2026
- Vol 3a - Figure 6.15 - Wildfowl and Waders Spring 2026
- Vol 3a - Figure 6.16 - Target Raptor sp flights Spring 2026
- Vol 3a - Figure 6.17 - Goose survey
- Vol 3a - Figure 6.18 - Goose spa
- Vol 3a - Figure 6.19 - Golden Eagle Topographic Model
Chapter 7 - Ecology
- Vol 3a - Figure 7.1 - Designated Sites
- Vol 3a - Figure 7.2 - NVC Communities
- Vol 3a - Figure 7.3.0 - 7.3.9 - Potential GWDTEs
- Vol 3a - Figure 7.4 a-b - Bat Roost Assessment
Chapter 8 - Geology, soils, peat
- Vol 3a - Figure 8.1 - Solid Geology
- Vol 3a - Figure 8.2 - Drift Geology
- Vol 3a - Figure 8.3 - Macaulay Soils Map
- Vol 3a - Figure 8.4 - Site Visit Features
- Vol 3a - Figure 8.5 - Peat Probe Survey Results
- Vol 3a - Figure 8.6 - Peat Depth Interpolation
- Vol 3a - Figure 8.7 - Hydrogeology
Chapter 9 - Surface Water
- Vol 3a - Figure 9.1 - Surface Water Receptors
- Vol 3a - Figure 9.2 - Private Water Supplies
- Vol 3a - Figure 9.3 - Private Water Supplies with SEPA Buffer Zones
Chapter 10 - Cultural Heritage
- Vol 3a - Figure 10.1 - Cultural Heritage Assets in the Inner Study Area
- Vol 3a - Figure 10.2a - Cultural Heritage 5km Outer Study Area
- Vol 3a - Figure 10.2b - Cultural Heritage Viewpoints
- Vol 3a - Figure 10.3 - Cultural Heritage 10km Outer Study Area
Chapter 11 Figures - Noise
- Vol 3a - Figure 11.1a - Cumulative Noise Contours and Receptors
- Vol 3a - Figure 11.1b - Cumulative Noise Contours and Receptors
Chapter 13 Figures - Socio Ec
- Vol 3a - Figure 13.1 - Proposed Felling Plan
- Vol 3a - Figure 13.2 - Infrastructure Footprint Within Forestry
Chapter 14 Figures - Shadow Flicker
Vol 3b Part 1 LVIA Visulisations
- Vol 3b - Figure V3-1.1 - VP 1 A83 at Glenbarr Burial Ground - Location Plan
- Vol 3b - Figure V3-9.1 - VP 12 Kintyre Way (Bord a Dubh) - Location Plan
- Vol 3b - Figure V3b-1.2 - VP 1 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-1.3 - VP1 A83 at Glenbarr Burial Ground - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-1.4a - VP1 A83 at Glenbarr Burial Ground - Proposed Varied Development Wireline
- Vol 3b - Figure V3b-1.4b - VP1 A83 at Glenbarr Burial Ground - Consented Development Wireline
- Vol 3b - Figure V3b-1.5 - VP1 A83 at Glenbarr Burial Ground - Photomontage
- Vol 3b - Figure V3b-2.1 - VP 2 Glenbarr War Memorial - Location Plan
- Vol 3b - Figure V3b-2.2 - VP 2 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-2.3 - VP2 Glenbarr War Memorial - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-2.4a - VP2 Glenbarr War Memorial - Proposed Varied Development Wireline
- Vol 3b - Figure V3b-2.4b - VP2 Glenbarr War Memorial - Consented Development Wireline
- Vol 3b - Figure V3b-2.5 - VP2 Glenbarr War Memorial - Photomontage
- Vol 3b - Figure V3b-2.6 - VP2 Glenbarr War Memorial - Visible Aviation Lighting Photomontage
- Vol 3b - Figure V3b-3.1 - VP 4 Islay Ferry Route – Location Plan
- Vol 3b - Figure V3b-3.2 - VP 4 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-3.3 - VP4 Islay Ferry Route - Cumulative Wireline
- Vol 3b - Figure V3b-3.4a - VP4 Islay Ferry Route - Proposed Varied Development Wireline
- Vol 3b - Figure V3b-3.4b - VP4 Islay Ferry Route - Consented Development Wireline
- Vol 3b - Figure V3b-4.1 - VP 5 Gigha (South Pier) - Location Plan
- Vol 3b - Figure V3b-4.2 - VP 5 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-4.3 - VP5 Gigha (South Pier) - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-4.4a - VP5 Gigha (South Pier)- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-4.4b - VP5 Gigha (South Pier) - Consented Development Wireline
- Vol 3b - Figure V3b-4.5 - VP5 Gigha (South Pier) - Photomontage
- Vol 3b - Figure V3b-5.1 - VP 6 Machrihanish Seating Area (Little Scone) - Location Plan
- Vol 3b - Figure V3b-5.2 - VP 6 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-5.3 - VP6 Machrihanish Seating Area (Little Scone) - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-5.4a - VP6 Machrihanish Seating Area (Little Scone)- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-5.4b - VP6 Machrihanish Seating Area (Little Scone) - Consented Development Wireline
- Vol 3b - Figure V3b-5.5 - VP6 Machrihanish Seating Area (Little Scone) - Photomontage
- Vol 3b - Figure V3b-5.6 - VP6 Machrihanish Seating Area (Little Scone) - Visible Aviation Lighting Photomontage
- Vol 3b - Figure V3b-6.1 - VP 8 Southend Road - Location Plan
- Vol 3b - Figure V3b-6.2 - VP 8 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-6.3 - VP8 Southend Road - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-6.4a - VP8 Southend Road- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-6.4b - VP8 Southend Road - Consented Development Wireline
- Vol 3b - Figure V3b-6.5 - VP8 Southend Road - Photomontage
- Vol 3b - Figure V3b-7.1 - VP 9 Campbelton (Ralston Road) - Location Plan
- Vol 3b - Figure V3b-7.2 - VP 9 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-7.3 - VP9 Campbeltown (Ralston Road) - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-7.4a - VP9 Campbeltown (Ralston Road)- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-7.4b - VP9 Campbeltown (Ralston Road) - Consented Development Wireline
- Vol 3b - Figure V3b-7.5 - VP9 Campbelton (Ralston Road) - Photomontage
- Vol 3b - Figure V3b-8.1 - VP 10 Beinn Ghuilean - Location Plan
- Vol 3b - Figure V3b-8.2 - VP 10 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-8.3 - VP10 Beinn Ghuilean - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-8.4a - VP10 Beinn Ghuilean- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-8.4b - VP10 Beinn Ghuilean - Consented Development Wireline
- Vol 3b - Figure V3b-8.5 - VP10 Beinn Ghuilean - Photomontage
- Vol 3b - Figure V3b-9.2 - VP 12 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-9.3 - VP12 Kintyre Way (Bord a Dubh) - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-9.4a - VP12 Kintyre Way (Bord a Dubh)- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-9.4b - VP12 Kintyre Way (Bord a Dubh) - Consented Development Wireline
- Vol 3b - Figure V3b-9.5 - VP12 Kintyre Way (Bord a Dubh) - Photomontage
- Vol 3b - Figure V3b-10.1 - VP 16 Kilbrannan - Location Plan
- Vol 3b - Figure V3b-10.2 - VP 16 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-10.3 - VP16 Kilbrannan - Cumulative Wireline
- Vol 3b - Figure V3b-10.4a - VP16 Kilbrannan- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-10.4b - VP16 Kilbrannan - Consented Development Wireline
- Vol 3b - Figure V3b-11.1 - VP 17 Breakachy - Location Plan
- Vol 3b - Figure V3b-11.2 - VP 17 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-11.3 - VP17 Breakachy - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-11.4a - VP17 Breakachy- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-11.4b - VP17 Breakachy - Consented Development Wireline
- Vol 3b - Figure V3b-11.5 - VP17 Breakachy - Photomontage
- Vol 3b - Figure V3b-12.1 - VP 18 Kintyre Trail (Skeroblingarry) - Location Plan
- Vol 3b - Figure V3b-12.2 - VP 18 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-12.3 - VP18 Kintyre Trail (Skeroblingarry) - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-12.4a - VP18 Kintyre Trail (Skeroblingarry)- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-12.4b - VP18 Kintyre Trail (Skeroblingarry) - Consented Development Wireline
- Vol 3b - Figure V3b-12.5 - VP18 Kintyre Trail (Skeroblingarry) - Photomontage
- Vol 3b - Figure V3b-13.1 - VP 19 Drumlemble - Location Plan
- Vol 3b - Figure V3b-13.2 - VP 19 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-13.3 - VP19 Drumlemble - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-13.4a - VP19 Drumlemble- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-13.4b - VP19 Drumlemble - Consented Development Wireline
- Vol 3b - Figure V3b-13.5 - VP19 Drumlemble - Photomontage
- Vol 3b - Figure V3b-14.1 - VP 21 B842 north of Peninver Sands - Location Plan
- Vol 3b - Figure V3b-14.2 - VP 21 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-14.3 - VP21 B842 north of Peninver Sands - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-14.4a - VP21 B842 north of Peninver Sands- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-14.4b - VP21 B842 north of Peninver Sands - Consented Development Wireline
- Vol 3b - Figure V3b-14.5 - VP21 B842 north of Peninver Sands - Photomontage
- Vol 3b - Figure V3b-15.1 - VP 23 Beinn Bharrain - Location Plan
- Vol 3b - Figure V3b-15.2 - VP 23 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-15.3 - VP23 Beinn Bharrain - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-15.4a - VP23 Beinn Bharrain- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-15.4b - VP23 Beinn Bharrain - Consented Development Wireline
- Vol 3b - Figure V3b-15.5 - VP23 Beinn Bharrain - Photomontage
- Vol 3b - Figure V3b-15.6 - VP23 Beinn Bharrain - Visible Aviation Lighting Photomontage
- Vol 3b - Figure V3b-16.1 - VP 24 Sea near Machrihanish - Location Plan
- Vol 3b - Figure V3b-16.2 - VP 24 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-16.3 - VP24 Sea near Machrihanish - Cumulative Wireline
- Vol 3b - Figure V3b-16.4a - VP24 Sea near Machrihanish- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-16.4b - VP24 Sea near Machrihanish - Consented Development Wireline
- Vol 3b - Figure V3b-17.1 - VP 27 Machrihanish Dunes - Location Plan
- Vol 3b - Figure V3b-17.2 - VP 27 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-17.3 - VP27 Machrihanish Dunes - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-17.4a - VP27 Machrihanish Dunes- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-17.4b - VP27 Machrihanish Dunes - Consented Development Wireline
- Vol 3b - Figure V3b-17.5 - VP27 Machrihanish Dunes - Photomontage
- Vol 3b - Figure V3b-18.1 - VP 28 Dougarie Point – Location Plan
- Vol 3b - Figure V3b-18.2 - VP 28 - Baseline Photo and Wireline of Existing Tangy Wind Farm
- Vol 3b - Figure V3b-18.3 - VP28 Dougarie Point - Baseline Photo and Cumulative Wireline
- Vol 3b - Figure V3b-18.4a - VP28 Dougarie Point- Proposed Varied Development Wireline
- Vol 3b - Figure V3b-18.4b - VP28 Dougarie Point- Consented Varied Development Wireline
- Vol 3b - Figure V3b-18.5 - VP28 Dougarie Point - Photomontage
Vol 3b part 2 Cultural Hertiage Visulisations
- Vol 3b - Figure V3b-10.4.1- Cultural Heritage Viewpoint 1 - Tangy Loch Fortified Dwelling (SM3180) - Proposed Varied Development
- Vol 3b - Figure V3b-10.4.2- Cultural Heritage Viewpoint 1 - Tangy Loch Fortified Dwelling (SM3180) - Consented Development
- Vol 3b - Figure V3b-10.4.3- Cultural Heritage Viewpoint 1 - Tangy Loch Fortified Dwelling (SM3180) - Cumulative Wireline
- Vol 3b - Figure V3b-10.5.1- Cultural Heritage Viewpoint 2 - Tangy Loch Fortified Dwelling (SM3180) - Proposed Varied Development
- Vol 3b - Figure V3b-10.5.2- Cultural Heritage Viewpoint 2 - Tangy Loch Fortified Dwelling (SM3180) - Consented Development
- Vol 3b - Figure V3b-10.5.3- Cultural Heritage Viewpoint 2 - Tangy Loch Fortified Dwelling (SM3180) - Cumulative Wireline
- Vol 3b - Figure V3b-10.5.4- Cultural Heritage Viewpoint 2 - Tangy Loch Fortified Dwelling (SM3180) - Photomontage
- Vol 3b - Figure V3b-10.6.1-Cultural Heritage Viewpoint 3 - Killocraw, Cairn 640m E of (SM3647) - Proposed Varied Development
- Vol 3b - Figure V3b-10.6.2-Cultural Heritage Viewpoint 3 - Killocraw, Cairn 640m E of (SM3647) - Consented Development
- Vol 3b - Figure V3b-10.6.3-Cultural Heritage Viewpoint 3 - Killocraw, Cairn 640m E of (SM3647) - Cumulative Wireline
- Vol 3b - Figure V3b-10.6.4-Cultural Heritage Viewpoint 3 - Killocraw, Cairn 640m E of (SM3647) - Photomontage
- Vol 3b - Figure V3b-10.7.1-Cultural Heritage Viewpoint 4 - Killocraw Cairn, 450m ESE of (SM3664) - Proposed Varied Development
- Vol 3b - Figure V3b-10.7.2-Cultural Heritage Viewpoint 4 - Killocraw Cairn, 450m ESE of (SM3664) - Consented Development
- Vol 3b - Figure V3b-10.7.3-Cultural Heritage Viewpoint 4 - Killocraw Cairn, 450m ESE of (SM3664) - Cumulative Wireline
- Vol 3b - Figure V3b-10.7.4-Cultural Heritage Viewpoint 4 - Killocraw Cairn, 450m ESE of (SM3664) - Photomontage
- Vol 3b - Figure V3b-10.8.1-Cultural Heritage Viewpoint 5 - View towards both Killocraw Cairn, 450m ESE of (SM3664) -Proposed Varied Development
- Vol 3b - Figure V3b-10.8.2-Cultural Heritage Viewpoint 5 - View towards both Killocraw Cairn, 450m ESE of (SM3664) - Consented Development
- Vol 3b - Figure V3b-10.8.3-Cultural Heritage Viewpoint 5 - View towards both Killocraw Cairn, 450m ESE of (SM3664) -Cumulative Wireline
- Vol 3b - Figure V3b-10.8.4-Cultural Heritage Viewpoint 5 - Photomontage
- Vol 3b - Figure V3b-10.9.1-Cultural Heritage Viewpoint 6 - Killocraw cup marked stone 800m E of (SM209) - Proposed Varied Development
- Vol 3b - Figure V3b-10.9.2-Cultural Heritage Viewpoint 6 - Killocraw cup marked stone 800m E of (SM209) - Consented Development
- Vol 3b - Figure V3b-10.9.3-Cultural Heritage Viewpoint 6 - Killocraw cup marked stone 800m E of (SM209) - Cumulative Wireline
- Vol 3b - Figure V3b-10.10.1-Cultural Heritage Viewpoint 7 - Killocraw, Fort NW of (SM3066) - Proposed Varied Development
- Vol 3b - Figure V3b-10.10.2-Cultural Heritage Viewpoint 7 - Killocraw, Fort NW of (SM3066) - Consented Development
- Vol 3b - Figure V3b-10.10.3-Cultural Heritage Viewpoint 7 - Killocraw, Fort NW of (SM3066) - Cumulative Wireline
- Vol 3b - Figure V3b-10.11.1-Cultural Heritage Viewpoint 8 - Dun Fhinn, dun 300m W of Killocraw (SM3663) - Proposed Varied Development
- Vol 3b - Figure V3b-10.11.2-Cultural Heritage Viewpoint 8 - Dun Fhinn, dun 300m W of Killocraw (SM3663) - Consented Development
- Vol 3b - Figure V3b-10.11.3-Cultural Heritage Viewpoint 8 - Dun Fhinn, dun 300m W of Killocraw (SM3663) - Cumulative Wireline
- Vol 3b - Figure V3b-10.12.1-Cultural Heritage Viewpoint 9 - Dun Putechantuy, dun, Kintyre (SM3224) - Proposed Varied Development
- Vol 3b - Figure V3b-10.12.2-Cultural Heritage Viewpoint 9 - Dun Putechantuy, dun, Kintyre (SM3224) - Consented Development
- Vol 3b - Figure V3b-10.12.3-Cultural Heritage Viewpoint 9 - Dun Putechantuy, dun, Kintyre (SM3224) - Cumulative Wireline
- Vol 3b - Figure V3b-10.13.1-Cultural Heritage Viewpoint 10 - Bellochantuy, dun (SM3062) - Proposed Varied Development
- Vol 3b - Figure V3b-10.13.2-Cultural Heritage Viewpoint 10 - Bellochantuy, dun (SM3062) - Consented Development
- Vol 3b - Figure V3b-10.13.3-Cultural Heritage Viewpoint 10 - Bellochantuy, dun (SM3062) - Cumulative Wireline
- Vol 3b - Figure V3b-10.14.1-Cultural Heritage Viewpoint 11 - Port a’Chaisteil, dun 505m SSW of Tangy Lodge (SM3273) - Proposed Varied Development
- Vol 3b - Figure V3b-10.14.2-Cultural Heritage Viewpoint 11 - Port a’Chaisteil, dun 505m SSW of Tangy Lodge (SM3273) - Consented Development
- Vol 3b - Figure V3b-10.14.3-Cultural Heritage Viewpoint 11 - Port a’Chaisteil, dun 505m SSW of Tangy Lodge (SM3273) - Cumulative Wireline
- Vol 3b - Figure V3b-10.15.1-Cultural Heritage Viewpoint 12 - Port nam Marbh, dun W of Drumalea (SM3272) - Proposed Varied Development
- Vol 3b - Figure V3b-10.15.2-Cultural Heritage Viewpoint 12 - Port nam Marbh, dun W of Drumalea (SM3272) - Consented Development
- Vol 3b - Figure V3b-10.15.3-Cultural Heritage Viewpoint 12 - Port nam Marbh, dun W of Drumalea (SM3272) - Cumulative Wireline
- Vol 3b - Figure V3b-10.16.1-Cultural Heritage Viewpoint 13 - Westport, fort 240m N of (SM3274) - Proposed Varied Development Wireline
- Vol 3b - Figure V3b-10.16.2-Cultural Heritage Viewpoint 13 - Westport, fort 240m N of (SM3274) - Consented Development Wireline
- Vol 3b - Figure V3b-10.16.3-Cultural Heritage Viewpoint 13 - Westport, fort 240m N of (SM3274) - Cumulative Wireline
- Vol 3b - Figure V3b-10.17.1-Cultural Heritage Viewpoint 14 - Largiemore, fort NE of (SM3063) - Proposed Varied Development
- Vol 3b - Figure V3b-10.17.2-Cultural Heritage Viewpoint 14 - Largiemore, fort NE of (SM3063) - Consented Development
- Vol 3b - Figure V3b-10.17.3-Cultural Heritage Viewpoint 14 - Largiemore, fort NE of (SM3063) - Cumulative Wireline
- Vol 3b - Figure V3b-10.18.1-Cultural Heritage Viewpoint 15 -Skeroblin Hill, cairn (SM3108) - Proposed Varied Development
- Vol 3b - Figure V3b-10.18.2-Cultural Heritage Viewpoint 15 - Skeroblin Hill, cairn (SM3108) - Consented Development
- Vol 3b - Figure V3b-10.18.3-Cultural Heritage Viewpoint 15 - Skeroblin Hill, cairn (SM3108) - Cumulative Wireline
- Vol 3b - Figure V3b-10.19.1-Cultural Heritage Viewpoint 16 -Ranachan Hill, fort (SM3064) - Proposed Varied Development
- Vol 3b - Figure V3b-10.19.2-Cultural Heritage Viewpoint 16 - Ranachan Hill, fort (SM3064) - Consented Development
- Vol 3b - Figure V3b-10.19.3-Cultural Heritage Viewpoint 16 - Ranachan Hill, fort (SM3064) - Cumulative Wireline
- Vol 3b - Figure V3b-10.20.1-Cultural Heritage Viewpoint 17 -Killocraw, cup-markings (WoSAS 3086) - Proposed Varied Development
- Vol 3b - Figure V3b-10.20.2-Cultural Heritage Viewpoint 17 - Killocraw, cup-markings (WoSAS 3086) - Consented Development
- Vol 3b - Figure V3b-10.20.3-Cultural Heritage Viewpoint 17 - Killocraw, cup-markings (WoSAS 3086) - Cumulative Wireline
Chapter 1
Chapter 3
- Vol 4 - Technical Appendix 3.1 - Scoping Report
- Vol 4 - Technical Appendix 3.2 - Scoping Opinion
- Vol 4 - Technical Appendix 3.3 - Gatecheck 1 Report
- Vol 4 - Technical Appendix 3.4 - Post Scoping Pre-application Consultation
- Vol 4 - Technical Appendix 3.5 - Tangy IV Cnoc Buidhe WF 132 kV OHL Shared Use Connection - EIA Scoping Report
- Vol 4 - Technical Appendix 3.6 - Tangy IV Cnoc Buidhe WF 132 kV OHL Shared Use EIA Scoping Opinion
- Vol 4 - Technical Appendix 3.7 - Planning Conditions Summary
- Vol 4 - Technical Appendix 3.7a - Construction Environment Management Plan
- Vol 4 - Technical Appendix 3.7a - Construction Environment Management Plan - Appendices
- Appendix 1 Environmental Constraints Map
- Appendix 2 MS-SHE-010 Incident Reporting and Investigation Standard
- Appendix 3 Peat Depth Plan
- Appendix 4 Species Protection Plan - Badger
- Appendix 4 Species Protection Plan - Bat
- Appendix 4 Species Protection Plan - Otter
- Appendix 4 Species Protection Plan - PM and RS
- Appendix 4 Species Protection Plan - Water vole
- Appendix 5 Bird Protection Plan
- Appendix 6 Water Quality and Fish Monitoring Plan
- Appendix 7 Private Water Supply Risk Assessment (Access Track)
- Appendix 8 Archaeology Written Scheme of Investigation
- Vol 4 - Technical Appendix 3.7a - Construction Environment Management Plan - Appendices
- Vol 4 - Technical Appendix 3.7b - Species Protection Plan Birds
- Vol 4 - Technical Appendix 3.7c - Outline Decommissioning Method Statement Tangy I & II
- Vol 4 - Technical Appendix 3.7d - Tangy IV Compensatory Planting
Chapter 5 - LVIA
- Vol 4 Technical Appendix 5.4
- Vol 4 - Technical Appendix 5.4 - Assessment of Designated and Protected Landscapes COVER
- Vol 4 - Technical Appendix 5.4 - Assessment of Designated and Protected Landscapes
- Vol 4 - Fig TA 5.4-1 Map of Relative Wildness (WLA 03)
- Vol 4 - Technical Appendix 5.4 - Assessment of Designated and Protected Landscapes
- Vol 4 - Technical Appendix 5.4 - Assessment of Designated and Protected Landscapes
- Vol 4 Technical Appendix 5.9
- Figure TA5.9-7 Property 6 Killarow Farm - Proposed Varied Development Wireline
- Vol 4 - Technical Appendix 5.9 - Residential Visual Amenity Assessment COVER
- Vol 4 - Technical Appendix 5.9 - Residential Visual Amenity Assessment
- Vol 4 - Technical Appendix 5.9 - Residential Visual Amenity Assessment
- Vol 4 - Fig TA5.9-1 Residential Property Locations with ZTV
- Vol 4 - Fig TA5.9-2 Property 1 Killocraw Farm - PVD Wireline
- Vol 4 - Fig TA5.9-3a-b Property 2 Tighnamoile - PVD Wireline
- Vol 4 - Fig TA5.9-4a-b Property 3 Tangy Moil Farm - PVD Wireline
- Vol 4 - Fig TA5.9-5 Property 4 Gobagrennan Cottage - PVD Wireline
- Vol 4 - Fig TA5.9-6a-b Property 5 Tigh na Mara - PVD Wireline
- Vol 4 - Fig TA5.9-7 Property 6 Killarow Farm - PVD Wireline
- Vol 4 - Fig TA5.9-8 Property 7 Maleen - PVD Wireline
- Vol 4 - Fig TA5.9-9 Property 8 Killarow Cottage - PVD Wireline
- Vol 4 - Fig TA5.9-10 Property 9 Tangy Cottage - PVD Wireline
- Vol 4 - Fig TA5.9-11 Property 10 Drumlea Farm Cottage - PVD Wireline
- Vol 4 - Fig TA5.9-12 Property 11 Tangy Smithy - PVD Wireline
- Vol 4 - Fig TA5.9-13 Property 12 Tangy Mill - PVD Wireline
- Vol 4 - Fig TA5.9-14 Property 13 Tangy Mill Croft - PVD Wireline
- Vol 4 - Fig TA5.9-15 Property 14 Tangy Farm - PVD Wireline
- Vol 4 - Fig TA5.9-16 Property 15 Tangy Lea Cottage - PVD Wireline
- Vol 4 - Fig TA5.9-17 Property 16 Drumalea Farm - PVD Wireline
- Vol 4 - Fig TA5.9-18a-b Property 17 Dalnaspidal-Hazel’s Cottage - PVD Wireline
- Vol 4 - Fig TA5.9-19 Property 18 Breakachy -No 4 - PVD Wireline
- Vol 4 - Fig TA5.9-20 Property 19 Breakachy House - PVD Wireline
- Vol 4 - Fig TA5.9-21 Property 20 Breakachy -No 5 - PVD Wireline
- Vol 4 - Fig TA5.9-22 Property 21 Breakachy -No 6 - PVD Wireline
- Vol 4 - Fig TA5.9-23 Property 22 High Ballevain Farm - PVD Wireline
- Vol 4 - Technical Appendix 5.9 - Residential Visual Amenity Assessment
- Vol 4 Technical Appendix 5.10
- Vol 4 - Fig TA5.10-1a Visible Aviation Light Hub Height ZTV A3
- Vol 4 - Fig TA5.10-1b Visible Aviation Light Hub Height ZTV A1
- Vol 4 - Fig TA5.10-2 Visible Aviation Light Theoretical Intensity ZTV
- Vol 4 - Fig TA5.10-3 Visible Aviation Light LCTs with Theoretical Intensity ZTV
- Vol 4 - Fig TA5.10-4 Visible Aviation Light Desig Protected Lscapes with Theoretical Intensity ZTV
- Vol 4 - Fig TA5.10-5 Visible Aviation Light Visual Receptors with Theoretical Intensity ZTV
- Vol 4 - Technical Appendix 5.10 - Landscape and Visual Assessment of Aviation Lighting
- Vol 4 - Technical Appendix 5.1 - Assessment and Technical Methodologies
- Vol 4 - Technical Appendix 5.2 - Summary of Scoping Process
- Vol 4 - Technical Appendix 5.3 - Assessment of Landscape Character Types
- Vol 4 - Technical Appendix 5.5 - Existing and Proposed Wind Energy Developments within 60km
- Vol 4 - Technical Appendix 5.6 - Cumulative Landscape Assessment Tables
- Vol 4 - Technical Appendix 5.7 - Visual Assessment Tables
- Vol 4 - Technical Appendix 5.8 - Cumulative Visual Assessment Tables
Chapter 6
- Vol 4 - Technical Appendix 6.1 - Ornithology Technical Report
- Vol 4 - Technical Appendix 6.2 - Shadow Habitats Regulations Appraisal Report
Chapter 7 - Ecology and Nature Conservation
- Vol 4 - Technical Appendix 7.1 - Biodiversity Net Gain Assessment
- Vol 4 - Technical Appendix 7.2 - Habitat Management Plan for Proposed Varied Development
Chapter 8
- Vol 4 - Figure TA8.1.1 - Peat Excavation
- Vol 4 - Technical Appendix 8.1 - Updated Preliminary Peat Management Plan
- Vol 4 - Technical Appendix 8.2 - Updated Carbon Balance Assessment
Chapter 9
- Vol 4 - Technical Appendix 9.1 - Private Water Supply Assessment
- Vol 4 - Technical Appendix 9.2 - Environmental Authorisation (Scotland) Regulations Licences
- Vol 4 - Technical Appendix 9.3 - Assessment Methodology
Chapter 10 - Cultural Heritage
- Vol 4 - Technical Appendix 10.1 - Additional Cultural Heritage Assets in the Inner Study Area
- Vol 4 - Technical Appendix 10.2 - Cultural Heritage Asset Setting Assessment
- Vol 4 - Technical Appendix 10.3 - Cultural Heritage Assets in the Outer Study Area with No Predicted Visibility
- Vol 4 - Technical Appendix 10.4 - Revised Cultural Heritage Viewpoints
Chapter 11
- Vol 4 - Technical Appendix 11.1 - Baseline Noise Data Reanalysis
- Vol 4 - Technical Appendix 11.2 - Site Specific Noise Limit Derivation
Chapter 12
Chapter 14
Chapter 15 Aviation
- Vol 4 - Technical Appendix 15.1 - Tangy IV Lighting Report (Wind Farm Low Flying Aviation Consultants (WFLFAC))
- Vol 4 - Technical Appendix 15.2 - Civil Aviation Authority (CAA) Response to Tangy IV Wind Farm Aviation Lighting Assessment Report_Redacted
- Vol 4 - Technical Appendix 15.3 - Safeguarding Report
- Vol 4 - Technical Appendix 15.4 - Technical and Operational Assessment (TOPA) Report
Chapter 16
- Tangy IV S36C - Planning Statement
- Tangy IV S36C - PAC Report
- Tangy IV S36C - Socio-Economic Report
- Tangy IV S36C -Peat Landslide Hazard Risk Assessment (PLHRA)
- Figures for PLHRA
- Tangy IV S36C - PLHRA - Figure 1- Site Location Plan
- Tangy IV S36C - PLHRA - Figure 2 - Site Layout Plan
- Tangy IV S36C - PLHRA - Figure 3 - Site Features
- Tangy IV S36C - PLHRA - Figure 4 - Topography
- Tangy IV S36C - PLHRA - Figure 5 - Superficial Geology
- Tangy IV S36C - PLHRA - Figure 6 - Carbon & Peatland
- Tangy IV S36C - PLHRA - Figure 7 - National Soil Map
- Tangy IV S36C - PLHRA - Figure 8 - Bedrock Geology
- Tangy IV S36C - PLHRA - Figure 9 - Geomorphology
- Tangy IV S36C - PLHRA - Figure 10 - Peat Probe Locations and Depths
- Tangy IV S36C - PLHRA - Figure 11 - Peat Depth Interpolation
- Tangy IV S36C - PLHRA - Figure 12 - Peat Slide Assessed Risk
Tangy IV S36C Variation - project redesign
- Tangy IV - S36C Scoping Report - July 2025
- Figure 1 - S36C Scoping Report Proposed Varied Development Layout
- Figure 1.1 - S36C Scoping Report Proposed Varied Development Layout and Consented Layout
- Figure 1.2 - 2018 EIAR Site Location Plan
- Figure 1.3 - 2018 EIAR Site Layout (Consented Development)
- Figure 10.1 - Cultural Heritage - Outer Study Area and 200m Tip Height ZTV
- Figure 15.1 - Aviation Study Area and Locations
- Figure 5.1 - Proposed Viewpoints with Comparative ZTV
- Figure 5.2 - Designated and Protected Landscapes with Comparative ZTV
- Figure 5.3 - Landscape Character Types with ZTV
- Figure 5.4 - Visual Receptors with Comparative ZTV
- Figure 5.5a - VP1 A83 at Glenbarr Burial Ground - Location Plan
- Figure 5.5b - VP1 A83 at Glenbarr Burial Ground - Baseline Photo and Wireline (Consented Development)
- Figure 5.5c - VP1 A83 at Glenbarr Burial Ground - Baseline Photo and Wireline (Varied Development)
- Figure 5.6a - VP6 Machrihanish Seating Area (Little Scone) - Location Plan
- Figure 5.6b - VP6 Machrihanish Seating Area (Little Scone) - Baseline Photo and Wireline (Consented Development)
- Figure 5.6c - VP6 Machrihanish Seating Area (Little Scone) - Baseline Photo and Wireline (Varied Development)
- Figure 5.7a - VP8 Southend Road - Location Plan
- Figure 5.7b - VP8 Southend Road - Baseline Photo and Wireline (Consented Development)
- Figure 5.7c - VP8 Southend Road - Baseline Photo and Wireline (Varied Development)
- Figure 5.8a - VP21 B842 North of Peninver Sands - Location Plan
- Figure 5.8b - VP21 B842 North of Peninver Sands - Baseline Photo and Wireline (Consented Development)
- Figure 5.8c - VP21 B842 North of Peninver Sands - Baseline Photo and Wireline (Varied Development)
- Figure 5.9a - VP23 Beinn Bharrain - Location Plan
- Figure 5.9b VP23 Beinn Vharrain - Baseline Photo and Wireline (Consented Development)
- Figure 5.9c VP23 Beinn Vharrain - Baseline Photo and Wireline (Varied Development)
Tangy IV S36
- R170_1106_Ch1_Introduction_6
- R170_1106_Ch2_EIA_5
- R170_1106_Ch3_REPolicy_4
- R170_1106_Ch4 Site Selection_5
- R170_1106_Ch5_DesOfDev_5
- R170_1106_Ch6_Planning_4
- R170_1106_Ch7_ScopingConsultation_3
- R170_1106_Ch8_LVIA_5
- R170_1106_Ch9_Ornithology_5
- R170_1106_Ch10_Ecology_6
- R170_1106_Ch11_Geology_6
- R170_1106_Ch12_Water_5
- R170_1106_Ch13_CulHer_5
- R170_1106_Ch14_Noise_4
- R170_1106_Ch15_Traffic_4
- R170_1106_Ch16_LanduseSocioEconRec_6
- R170_1106_Ch17_ShadowFlicker_5
- R170_1106_Ch18_Aviation_5
- R170_1106_Ch19_ScheduleOfMitigation_2
- R170_1106_Glossary_AbbreviationsDefinitions_1
- Fig1.1_SiteLocation_SSE_2
- Fig1.2_EnvDesig_SSE_2
- Fig4.1a_DesignIteration_2
- Fig4.1b_DesignIteration_2
- Fig4.1c_DesignIteration_2
- Fig4.2_Comparative Wireline VP2 Glenbarr War Memorial_1
- Fig4.3_Comparative Wireline VP6 Machrihanish Little Scone_1
- Fig4.4_Comparative Wireline VP8 Southend Road_1
- Fig5.1_SiteLayout_SSE_2
- Fig5.2_IndicativeTurbineDimensions_SSE_2
- Fig5.3_IndicativeTurbineFoundation_SSE_2
- Fig5.4_IndicativeAccessTrackDetail_SSE_2
- Fig5.5_IndicativeSubstationPlan_SSE_2
- Fig5.6_IndicativeSubstationElevations_SSE_2
- Fig5.7_IndicativeMastElevations_SSE_2
- Fig5.8_IndicTempConstructionCompoundLayout_SSE_2
- Fig5.9_IndicativeCableTrenchDetail_SSE_2
- Fig5.10a_IndicativeOperationsBuildingLayout_SSE_2
- Fig5.10b_IndicativeOperationsBuildingExternalElevations_SSE_2
- Fig5.10c_IndicativeOperationsCompound_SSE_2
- Fig6.1_ArgyllandButeSpatialFramework_1
- Fig8.1.1_Zone of Theoretical Visibility (A3)_2
- Fig8.1.2_Zone of Theoretical Visibility (A1)_2
- Fig8.2_Comparative ZTV of the Existing and Proposed Development_2
- Fig8.3_Study Area_2
- Fig8.4_Cumulative Sites within 60km_2
- Fig8.5.1_Landscape Designations_2
- Fig8.5.2_Landscape Designations with ZTV_2
- Fig8.6.1_Landscape Character Types_2
- Fig8.6.2_Landscape Character Types with ZTV_2
- Fig8.7_Viewpoints and Visual Receptors within Study Area_2
- Fig8.8.1-2_Detailed Visual Receptor Locations_2
- Fig8.10.1_Cumulative ZTV_Tangy IV and Operational, Consented and Application_Appeal Sites_2
- Fig8.10.2_Cumulative ZTV- Tangy IV and Operational and Consented Sites_2
- Fig8.10.3_Cumulative ZTV- Tangy IV and Operational Sites_2
- Fig8.10.4.1_Cumulative ZTV- Tangy IV, Beinn an Tuirc 1,2&3_2
- Fig8.10.4.2_Cumulative ZTV- Tangy IV, Auchadaduie and Blary Hill_2
- Fig8.10.4.3_Cumulative ZTV- Tangy IV, Clachaig Glen and Killean Estate_2
- Fig8.10.4.4_Cumulative ZTV- Tangy IV, Cour and Deucheran Hill_2
- Fig8.10.4.5_Cumulative ZTV- Tangy IV, Gigha and GighaExt_2
- Fig8.10.4.6_Cumulative ZTV- Tangy IV, Eascairt and Freasdail_2
- Fig8.10.4.7_Cumulative ZTV- Tangy IV,Airigh and Gartnagrenach_2
- Fig8.10.4.8_Cumulative ZTV- Tangy IV, Auchenhoan Cottage and Kildalloig Farm_2
- Fig8.10.4.9_Cumulative ZTV- Tangy IV, Allt Dearg and Srondoire_2
- Fig8.10.4.10_Cumulative ZTV- Tangy IV, Auchentirrie Farm and Hunterston_2
- Fig8.10.4.11_Cumulative ZTV- Tangy IV, Ardrossan, Ardrossan Ext. and Sorbie Farm_2
- Fig8.10.4.12_Cumulative ZTV- Tangy IV, Girvan Hospital and Balsalloch Farm_2
- Fig8.10.4.13_Cumulative ZTV- Tangy IV and Islay Community Wind Energy Project_2
- Fig9.1_DS_20K_TANIV
- Fig9.2_SB_SA_TANIV
- Fig9.3_VP_VS_TANIV
- Fig9.4_WPC_TANIV
- Fig9.5_VPFA_CU_TANIV
- Fig9.6_VPFA_WF_TANIV
- Fig9.7_VPFA_GJ_TANIV
- Fig9.8_VPFA_HH_TANIV
- Fig9.9_VPFA_HG_TANIV
- Fig9.10_VPFA_OC_TANIV
- Fig9.11_VPFA_PE_TANIV
- Fig9.12_VPFA_BY_TANIV
- Fig9.13_VPFA_RH_TANIV
- Fig9.14_VPFA_WS_TANIV
- Fig9.15_VPFA_CS_TANIV
- Fig9.16_VPFA_EA_TANIV
- Fig9.17_VPFA_ML_TANIV
- Fig9.18_VPFA_SN_TANIV
- Fig9.19_VPFA_WK_TANIV
- Fig9.20_WaderActivity_TANIV
- Fig9.21_WWo_TANIV
- Fig9.22_Raptors_TANIV
- Figure 10.1 Designated Sites
- Figure 10.2 Phase 1 Habitat Survey
- Figure 10.3 NVC Habitat Survey
- Figure 10.4 Groundwater Dependant Terrestrial Ecosystems
- Figure 10.5 Great Crested Newt Survey
- Figure 10.6 Bat Transect Survey
- Figure 10.7 Static Bat Survey
- Figure 10.8 Otter and Pine Marten Survey
- Figure 10.10 Freshwater Invertebrates Survey
- Figure 10.11 Freshwater Pearl Mussel Survey
- Figure 10.12 Electric Fishing Survey
- Figure 10.13 Reptile Survey
- Figure 11.1 Aerial Plan
- Figure 11.2 Slope Plan
- Figure 11.3 Superficial Geology Plan
- Figure 11.4 Solid Geology Plan
- Figure 11.5 Peat Depth Plan
- Figure 11.6 Peat Stability Zonation Plan
- Figure 11.7 Peat Stability Zonation Plan - Post Mitigation
- Figure 11.8 Peat Stability Zonation Map - Mitigation T9 & 10
- Figure 11.9 Borrow Pit A Working Area and Profile
- Figure 11.10 Borrow Pit B Working Area and Profile
- Figure 11.11 Borrow Pit C Working Area and Profile
- Figure 11.12 Borrow Pit E Working Area and Profile
- Figure 12-1 Hydrological Features
- Figure 13.1 Heritage Assets within Site Boundary
- Figure 13.2 Designated Heritage Assets and 5km Study Area
- Figure 13.3 Designated Heritage Assets and 10km Study Area
- Figure 15.1 Abnormal Load Route
- Figure 15.2 Traffic Count Locations
- Figure 15.3 Construction Development Traffic Programme
- Figure 16.1 Felling
- Figure 16.2 Replanting
- Figure 17.1 Shadow Flicker Assessment Area
- Figure 13.3.1-4 Tangy Loch Fortified Dwelling (1)
- Figure 13.3.2.1-3 Tangy Loch Fortified Dwelling (2)
- Figure 13.3.3.1-4 Kilocraw Cairn
- Figure 13.3.4.1-3 Kilocraw Cairn Cup Marked Stone
- Figure 13.3.5.1 - 3 Kilocraw Fort
- Figure 13.3.6.1-2b Dun Fhinn Dun
- Figure 13.3.7.1-3 Putechantuy Dun
- Figure 13.3.8.1-4 Bellochantuy Dun
- Figure 13.3.9.1-3 Port a'Chasteil Dun
- Figure 13.3.10.1-3 Port nam Marbh Dun
- Figure 13.3.11.1-2 Westport Fort
- Figure 13.3.12.1-3 Largiemore Fort
- Figure 13.3.13.1-3 Skelribin Cairn
- Figure 13.3.14.1-3 Ranachan Hill Fort
- Figure 13.3.15.1-3 Kilocraw Cup Markings
- R170_1106_Fig8.9.1.1_Location Plan Viewpoint 1 A83 at Glenbarr Burial Ground_2
- R170_1106_Fig8.9.1.2_Existing Viewpoint 1 A83 at Glenbarr Burial Ground_2
- R170_1106_Fig8.9.1.3a-b_Cumulative Viewpoint 1 A83 at Glenbarr Burial Ground_2
- R170_1106_Fig8.9.1.4_Wireline Viewpoint 1 A83 at Glenbarr Burial Ground_2
- R170_1106_Fig8.9.1.5_Photomontage Viewpoint 1 A83 at Glenbarr Burial Ground_2
- R170_1106_Fig8.9.2.1_Location Plan Viewpoint 2 Glenbarr War Memorial_2
- R170_1106_Fig8.9.2.2_Existing Viewpoint 2 Glenbarr War Memorial_2
- R170_1106_Fig8.9.2.3a-c_Cumulative Viewpoint 2 Glenbarr War Memorial_2
- R170_1106_Fig8.9.2.4_Wireline Viewpoint 2 Glenbarr War Memorial_2
- R170_1106_Fig8.9.2.5_Photomontage Viewpoint 2 Glenbarr War Memorial_2
- R170_1106_Fig8.9.3.1 _Location Plan Viewpoint 3 Barr Glen_2
- R170_1106_Fig8.9.3.2_Existing Viewpoint 3 Barr Glen_2
- R170_1106_Fig8.9.3.3a-b_Cumulative Viewpoint 3 Barr Glen_2
- R170_1106_Fig8.9.3.4_Wireline Viewpoint 3 Barr Glen_2
- R170_1106_Fig8.9.3.5_Photomontage Viewpoint 3 Barr Glen_2
- R170_1106_Fig8.9.4.1_Location Plan Viewpoint 4 Islay Ferry Route_2
- R170_1106_Fig8.9.4.2_Existing Viewpoint 4 Islay Ferry Route_2
- R170_1106_Fig8.9.4.3a-b_Cumulative Viewpoint 4 Islay Ferry Route_2
- R170_1106_Fig8.9.4.4_Wireline Viewpoint 4 Islay Ferry Route_2
- R170_1106_Fig8.9.5.1 _Location Plan Viewpoint 5 Gigha (South Pier)_2
- R170_1106_Fig8.9.5.2_Existing Viewpoint 5 Gigha (South Pier)_2
- R170_1106_Fig8.9.5.3a-c_Cumulative Viewpoint 5 Gigha (South Pier)_2
- R170_1106_Fig8.9.5.4_Wireline Viewpoint 5 Gigha (South Pier)_2
- R170_1106_Fig8.9.5.5_Photomontage Viewpoint 5 Gigha (South Pier)_2
- R170_1106_Fig8.9.6.1_Location Plan Viewpoint 6 Machrihanish (Little Scone)_2
- R170_1106_Fig8.9.6.2_Existing Viewpoint 6 Machrihanish (Little Scone)_2
- R170_1106_Fig8.9.6.3_Cumulative Viewpoint 6 Machrihanish (Little Scone)_2
- R170_1106_Fig8.9.6.4_Wireline Viewpoint 6 Machrihanish (Little Scone)_2
- R170_1106_Fig8.9.6.5_Photomontage Viewpoint 6 Machrihanish (Little Scone)_2
- R170_1106_Fig8.9.7.1 _Location Plan Viewpoint 7 Stewarton_2
- R170_1106_Fig8.9.7.2_Existing Viewpoint 7 Stewarton_2
- R170_1106_Fig8.9.7.3_Cumulative Viewpoint 7 Stewarton_2
- R170_1106_Fig8.9.7.4_Wireline Viewpoint 7 Stewarton_2
- R170_1106_Fig8.9.7.5_Photomontage Viewpoint 7 Stewarton_2
- R170_1106_Fig8.9.8.1_Location Plan Viewpoint 8 Southend Road_2
- R170_1106_Fig8.9.8.2_Existing Viewpoint 8 Southend Road_2
- R170_1106_Fig8.9.8.3_Cumulative Viewpoint 8 Southend Road_2
- R170_1106_Fig8.9.8.4_Wireline Viewpoint 8 Southend Road_2
- R170_1106_Fig8.9.8.5_Photomontage Viewpoint 8 Southend Road_2
- R170_1106_Fig8.9.9.1_Location Plan Viewpoint 9 Campbeltown (Ralston Road)_2
- R170_1106_Fig8.9.9.2_Existing Viewpoint 9 Campbeltown (Ralston Road)_2
- R170_1106_Fig8.9.9.3a-b_Cumulative Viewpoint 9 Campbeltown (Ralston Road)_2
- R170_1106_Fig8.9.9.4_Wireline Viewpoint 9 Campbeltown (Ralston Road)_2
- R170_1106_Fig8.9.9.5_Photomontage Viewpoint 9 Campbeltown (Ralston Road)_2
- R170_1106_Fig8.9.10.1_Location Plan Viewpoint 10 Beinn Ghuilean_2
- R170_1106_Fig8.9.10.2_Existing Viewpoint 10 Beinn Ghuilean_2
- R170_1106_Fig8.9.10.3_Cumulative Viewpoint 10 Beinn Ghuilean_2
- R170_1106_Fig8.9.10.4_Wireline Viewpoint 10 Beinn Ghuilean_2
- R170_1106_Fig8.9.10.5_Photomontage Viewpoint 10 Beinn Ghuilean_2
- R170_1106_Fig8.9.11.1_Location Plan Viewpoint 11 High Peninver_2
- R170_1106_Fig8.9.11.2_Existing Viewpoint 11 High Peninver_2
- R170_1106_Fig8.9.11.3a-b_Cumulative Viewpoint 11 High Peninver_2
- R170_1106_Fig8.9.11.4_Wireline Viewpoint 11 High Peninver_2
- R170_1106_Fig8.9.11.5_Photomontage Viewpoint 11 High Peninver_2
- R170_1106_Fig8.9.12.1_Location Plan Viewpoint 12 Bord a Dubh (Kintyre Way)_2
- R170_1106_Fig8.9.12.2_Existing Viewpoint 12 Bord a Dubh (Kintyre Way)_2
- R170_1106_Fig8.9.12.3a-d_Cumulative Viewpoint 12 Bord a Dubh (Kintyre Way)_2
- R170_1106_Fig8.9.12.4_Wireline Viewpoint 12 Bord a Dubh (Kintyre Way)_2
- R170_1106_Fig8.9.12.5_Photomontage Viewpoint 12 Bord a Dubh (Kintyre Way)_2
- R170_1106_Fig8.9.13.1_Location Plan Viewpoint 13 A’ Cruach (Kintyre Way)_2
- R170_1106_Fig8.9.13.2_Existing Viewpoint 13 A’ Cruach (Kintyre Way)_2
- R170_1106_Fig8.9.13.3a-c_Cumulative Viewpoint 13 A’ Cruach (Kintyre Way)_2
- R170_1106_Fig8.9.13.4_Wireline Viewpoint 13 A’ Cruach (Kintyre Way)_2
- R170_1106_Fig8.9.13.5_Photomontage Viewpoint 13 A’ Cruach (Kintyre Way)_2
- R170_1106_Fig8.9.14.1_Location Plan Viewpoint 14 Allt a Choire_2
- R170_1106_Fig8.9.14.2_Existing Viewpoint 14 Allt a Choire_2
- R170_1106_Fig8.9.14.3a-b_Cumulative Viewpoint 14 Allt a Choire_2
- R170_1106_Fig8.9.14.4_Wireline Viewpoint 14 Allt a Choire_2
- R170_1106_Fig8.9.14.5_Photomontage Viewpoint 14 Allt a Choire_2
- R170_1106_Fig8.9.15.1_Location Plan Viewpoint 15 Ballywilline (Kintyre Way)_2
- R170_1106_Fig8.9.15.2_Existing Viewpoint 15 Ballywilline (Kintyre Way)_2
- R170_1106_Fig8.9.15.3_Cumulative Viewpoint 15 Ballywilline (Kintyre Way)_2
- R170_1106_Fig8.9.15.4_Wireline Viewpoint 15 Ballywilline (Kintyre Way)_2
- R170_1106_Fig8.9.15.5_Photomontage Viewpoint 15 Ballywilline (Kintyre Way)_2
- R170_1106_Fig8.9.16.1_Location Plan Viewpoint 16 Kilbrannan Sound_2
- R170_1106_Fig8.9.16.2_Existing Viewpoint 16 Kilbrannan Sound_2
- R170_1106_Fig8.9.16.3a-c_Cumulative Viewpoint 16 Kilbrannan Sound_2
- R170_1106_Fig8.9.16.4_Wireline Viewpoint 16 Kilbrannan Sound_2
- R170_1106_Fig8.9.17.1_Location Plan Viewpoint 17 Breakachy_2
- R170_1106_Fig8.9.17.2_Existing Viewpoint 17 Breakachy_2
- R170_1106_Fig8.9.17.3_Cumulative Viewpoint 17 Breakachy_2
- R170_1106_Fig8.9.17.4_Wireline Viewpoint 17 Breakachy_2
- R170_1106_Fig8.9.17.5_Photomontage Viewpoint 17 Breakachy_2
- R170_1106_Fig8.9.18.1_Location Plan Viewpoint 18 Skeroblingarry (Kintyre Way)_2
- R170_1106_Fig8.9.18.2_Existing Viewpoint 18 Skeroblingarry (Kintyre Way)_2
- R170_1106_Fig8.9.18.3_Cumulative Viewpoint 18 Skeroblingarry (Kintyre Way)_2
- R170_1106_Fig8.9.18.4_Wireline Viewpoint 18 Skeroblingarry (Kintyre Way)_2
- R170_1106_Fig8.9.18.5_Photomontage Viewpoint 18 Skeroblingarry (Kintyre Way)_2
- R170_1106_Fig8.9.19.1_Location Plan Viewpoint 19 Drumlemble_2
- R170_1106_Fig8.9.19.2_Existing Viewpoint 19 Drumlemble_2
- R170_1106_Fig8.9.19.3_Cumulative Viewpoint 19 Drumlemble_2
- R170_1106_Fig8.9.19.4_Wireline Viewpoint 19 Drumlemble_2
- R170_1106_Fig8.9.19.5_Photomontage Viewpoint 19 Drumlemble_2
- R170_1106_Fig8.9.20.1_Location Plan Viewpoint 20 Rhunahaorine Point (Kintyre Way)_2
- R170_1106_Fig8.9.20.2_Existing Viewpoint 20 Rhunahaorine Point (Kintyre Way)_2
- R170_1106_Fig8.9.20.3a-d_Cumulative Viewpoint 20 Rhunahaorine Point (Kintyre Way)_2
- R170_1106_Fig8.9.20.4_Wireline Viewpoint 20 Rhunahaorine Point (Kintyre Way)_2
- R170_1106_Fig8.9.20.5_Photomontage Viewpoint 20 Rhunahaorine Point (Kintyre Way)_2
- R170_1106_Fig8.9.21.1_Location Plan Viewpoint 21 B842 North of Peninver_2
- R170_1106_Fig8.9.21.2_Existing Viewpoint 21 B842 North of Peninver_2
- R170_1106_Fig8.9.21.3_Cumulative Viewpoint 21 B842 North of Peninver_2
- R170_1106_Fig8.9.21.4_Wireline Viewpoint 21 B842 North of Peninver_2
- R170_1106_Fig8.9.21.5_Photomontage Viewpoint 21 B842 of North Peninver_2
- R170_1106_Fig8.9.22.1_Location Plan Viewpoint 22 Campbeltown Airport_2
- R170_1106_Fig8.9.22.2_Existing Viewpoint 22 Campbeltown Airport_2
- R170_1106_Fig8.9.22.3a-b_Cumulative Viewpoint 22 Campbeltown Airport_2
- R170_1106_Fig8.9.22.4_Wireline Viewpoint 22 Campbeltown Airport_2
- R170_1106_Fig8.9.22.5_Photomontage Viewpoint 22 Campbeltown Airport_2
- R170_1106_Fig8.9.23.1_Location Plan Viewpoint 23 Beinn Bharrain_2
- R170_1106_Fig8.9.23.2_Existing Viewpoint 23 Beinn Bharrain_2
- R170_1106_Fig8.9.23.3a-c_Cumulative Viewpoint 23 Beinn Bharrain_2
- R170_1106_Fig8.9.23.4_Wireline Viewpoint 23 Beinn Bharrain_2
- R170_1106_Fig8.9.23.5_Photomontage Viewpoint 23 Beinn Bharrain_2
- R170_1106_Fig8.9.24.1_Location Plan Viewpoint 24 Sea near Machrihanish_2
- R170_1106_Fig8.9.24.2_Existing Viewpoint 24 Sea near Machrihanish_2
- R170_1106_Fig8.9.24.3a-b_Cumulative Viewpoint 24 Sea near Machrihanish_2
- R170_1106_Fig8.9.24.4_Wireline Viewpoint 24 Sea near Machrihanish_2
- R170_1106_Fig8.9.25.1_Location Plan Viewpoint 25 Ranachan Hill_2
- R170_1106_Fig8.9.25.2_Existing Viewpoint 25 Ranachan Hill_2
- R170_1106_Fig8.9.25.3a-c_Cumulative Viewpoint 25 Ranachan Hill_2
- R170_1106_Fig8.9.25.4_Wireline Viewpoint 25 Ranachan Hill_2
- R170_1106_Fig8.9.25.5_Photomontage Viewpoint 25 Ranachan Hill_2
- R170_1106_Fig8.9.26.1_Location Plan Viewpoint 26 Westport Beach_2
- R170_1106_Fig8.9.26.2_Existing Viewpoint 26 Westport Beach_2
- R170_1106_Fig8.9.26.3a-b_Cumulative Viewpoint 26 Westport Beach_2
- R170_1106_Fig8.9.26.4_Wireline Viewpoint 26 Westport Beach_2
- R170_1106_Fig8.9.26.5_Photomontage Viewpoint 26 Westport Beach_2
- R170 1106 Fig8.9.27.1 Location Plan Viewpoint 27 Machrihanish Dunes 2
- R170_1106_Fig8.9.27.2_Existing Viewpoint 27 Machrihanish Dunes_2
- R170_1106_Fig8.9.27.3_Cumulative Viewpoint 27 Machrihanish Dune_2
- R170_1106_Fig8.9.27.4_Wireline Viewpoint 27 Machrihanish Dunes_2
- R170_1106_Fig8.9.27.5_Photomontage Viewpoint 27 Machrihanish Dunes_2
- R170_1106_Fig8.11.1.1_Location Plan Viewpoint Ballygrogan Picnic Site_2
- R170_1106_Fig8.11.1.2_Additional Viewpoint Ballygrogan Picnic Site_2
- R170_1106_Fig8.11.2.1_Location Plan Viewpoint Goatfell, Arran_2
- R170_1106_Fig8.11.2.2a-c_Additional Viewpoint Goatfell, Arran_2
- R170_1106_Fig8.11.3.1_Location Plan Viewpoint Kilberry Road_2
- R170_1106_Fig8.11.3.2_Additional Viewpoint Kilberry Road_2
- R170_1106_TA5.1_CEMP_3
- R170_1106_TA5.2_CarbonBalance_2
- R170_1106_TA7.1_Combined_2
- R170_1106_TA8.1_TechMethodologies_3_clean
- R170_1106_TA8.2_Consultation_3_clean
- R170_1106_TA8.3_LVIAScopeIdentification_3_clean
- R170_1106_TA8.4_CumulativeSites_3_clean
- R170_1106_TA8.5_LandscapeAssessment_3_clean
- R170_1106_TA8.6_CumuLandscapeAssessment_3_clean
- R170_1106_TA8.7_VisualAssessment_3_clean
- R170_1106_TA8.8_CumuVisualAssessment_3_clean
- R170_1106_TA9.1_Ornithology_Combined_1
- R170_1106_TA10.1_SurveyMethodologyandResults_2
- R170_1106_TA10.2_BatSurvey_2
- R170_1106_TA10.3_FreshwaterInvertebrateResults_2
- R170_1106_TA10.4_Fish Habitat Survey Report_1
- R170_1106_TA10.5_BadgerProtectionPlan_2
- R170_1106_TA10.6_HMP_3
- R170_1106_TA11.1_PLHRA_2
- R170_1106_TA11.2_BorrowPit Report_2
- R170_1106_TA11.3_PMP_2
- R170_1106_TA12.1_SEPACorrs_1
- R170_1106_TA12.2_PWS_4
- R170_1106_TA12.3_CSM_5
- R170_1106_TA13.1_CulHerGazetteer_AOC_1
- R170_1106_TA13.2_SettingOfAsset_AOC_1
- R170_1106_TA13.3_AOC_2
- R170_1106_TA14.1_Noise_Combined_2_rfs
- R170_1106_TA15.1_ALRA_Combined_1
- R170_1106_TA15.2_OutlineTMP_Combined_1
- R170_1106_TA16.1_LongTermForestPlan_Combined_2
- R170_1106_TA17.1_ShadowFlicker_Combined_1
- R170_1106_TA18.1_Aviation and Radar Risk Assessment_1
- R170_1106_TA18.2_Instrument Flight Procedure Assessment_1
- Tangy IV - Scoping Report (April 2017) (Previously called modified Tangy III)
- Figure 1 - Site Location
- Figure 2 - Site Layout
- Figure 3 - Environmental Designations
- Figure 4A - ZTV of the existing development (75m tip height)
- Figure 4B ZTV of the ES 2014 layout (125m tip height)
- Figure 4C - ZTV of the Proposed Development (150m tip height)
- Figure 5 - Glen Barr Memorial
- Figure 6 - Machrihanish
- Figure 7 - Southend Road
We have undertaken significant stakeholder consultation (including three local public exhibitions), extensive site surveys and careful design to minimise any project impact. The turbine layout has been designed to utilise as much of the existing infrastructure as possible.
We recognise the importance of the opportunities that our projects can bring to local communities and businesses during construction and throughout its long-term operation the project is anticipated to bring significant local opportunities such as:
- Direct local employment both on site and within the local, regional and national supply chain;
- Procurement of local plant and materials; and
- Requirement for local accommodation for project staff.
- Planning statement
- Pre Application Consultation Report
- Design and Access Statement
- Vol2_EIA Report
- Additional Information - Cover Letter
- R170_1106_TA16.1_LongTermForestPlan_Combined_2
- R170_1106_TA17.1_ShadowFlicker_Combined_1
- R170_1106_TA18.1_Aviation and Radar Risk Assessment_1
- R170_1106_TA18.2_Instrument Flight Procedure Assessment_1
Forest figures
Tangy I S42
- Tangy I S42 Cover letter
- Tangy I and II Wind Farm Extension - Environmental Report
- Location Plan
- Appendix 1 - Figures
- Appendix 2 - OEMP
- Appendix 2 - Tangy Geese Flight Activity 2001-2004
- Appendix 2 - Tangy Moorland Bird Surveys 2006
- Appendix 3 - Operation Maintenance and Lifetime Extension Statements
- Tangy l ES 1994 - Volume 1 of 2
- Tangy ES l 1994 - Volume 2 of 2 Part A
- Tangy ES l 1994 - Volume 2 of 2 Part B
Tangy II S42
- S42 Application - Covering Letter
- Tangy I and II Wind Farm Life Extension - Environmental Report
- Location Plan
- Appendix 1 - Figures
- Appendix 2 - Supporting Information - OEMP
- Appendix 2 - Supporting Information - Tangy Geese Flight Activity 2001-04
- Appendix 2 - Supporting Information - Tangy Moorland Bird Surveys 2006
- Appendix 3 - Operational Maintenance and Lifetime Extension Statements
- Tangy I ES 1994 - Volume 1 of 2
- Tangy I ES 1994 Volume 2 of 2 PART A
- Tangy I ES 1994 Volume 2 of 2 PART B
- Tangy II ES 2004 PART A
- Tangy II ES 2004 PART B Landscape
- Tangy II ES 2004 Part C Landscape
- Tangy II ES 2004 PART D Birds
- Tangy II ES 2004 PART E Noise
News and views
SSE grateful for feedback at consultations for Tangy Repower Wind Farm

SSE is grateful to South Kintyre residents for their feedback on its plans for Tangy Repower Wind Farm provided at Public Exhibitions in Campbeltown, Machrihanish and Tayinloan at the end of August.
Public consultations were held to gather feedback on amended plans for the consented repowering project. These events are a key part of SSE’s engagement, and the local insights will help inform the submission of a Section 36C Variation consent application which SSE Renewables expects to submit to the Scottish Government in due course.
Ian Stewart, Lead Development Project Manager, SSE Renewables, said:
“It was great to get the chance to meet and chat with people from the communities in and around Tangy Wind Farm. To share our plans and hear the views of local residents is vital to the positive and considered development of the project.
“It was especially lovely to hear from local resident, Stewart MacMillan, who shared some photos and his diary entries with us going back to 23rd September 2002 when the first turbine blades were delivered to Tangy and then subsequently erected on September 27th 2002.”
If you were unable to attend our events, all exhibition materials are available on our website, and we’re always happy to hear from you directly too. The best contact for you to get in touch with is our Stakeholder Engagement Manager, Pauline Allison on Pauline.allison@sse.com / 07880 180662.

A link to our Feedback/Comments Forms for anyone who might like to still submit any comments over to us is here - Feedback Form Link. Even if you didn’t come to our events, it would still be great to gather local views on the re-design proposals.
SSE intend to run another round of Public Exhibitions around Spring 2026 ahead of submitting the Section 36C Variation application to the Scottish Government’s Energy Consents Unit (ECU).
In the interim period, the project will be undertaking additional surveys and revising relevant Environmental Assessments to ensure that the varied designs’ impacts are fully considered and assessed.
SSE RENEWABLES SHOWS CONTINUED SUPPORT FOR THE KINTYRE ULTRA
The Kintyre Ultra was given a much needed funding and volunteer boost this year, thanks to SSE Renewables.
The race, hosted in May each year, is renowned for its challenging terrain and breathtaking scenery, received a donation of £1,600 from the companies Tangy RePowering Development team, and some very appreciated ‘on the ground’ support from the onshore operations team.
This year, the 50.5km race was from Tayinloan to Tarbert with 960m of climb on a mix of beach, rough hill tracks and forest roads.
SSE Renewables volunteers above (Darren Munro, Tim Elliott, David Carr, Steven Smillie and Craig Scally) gave up their weekend to help out.
The team were up bright and early to travel to Tayinloan in West Kintyre where the race start point and the registration check in were located.
Their duties included collecting all the runners’ various drop bags and finish line bags to allow them to refuel etc. at the various check points.

A couple of the volunteers also positioned themselves at Seal Point layby to give the runners a much need water stop in the hot weather.
The organisers sent over a lovely message of thanks which is below:-
“Thank so much again for providing an excellent service on Saturday, delivering drop bags, bringing back signage and manning the extra drinks station. It makes a big difference to us, not having to go out for another day to collect the extra signs and with the weather being so hot, even early on it was good to be able to offer water for topping up.”
“Please pass on thanks to everyone involved.”

Anyone interested being involved again, either through entering or supporting then please save the 10th May 2025 in your diary!
ENDS
SSE RUNNERS AND VOLUNTEERS ENTER SPIRIT OF ARGYLL ULTRA RACE
22 May 2019
Saturday 11 May saw another successful Kintyre Way Ultra marathon take place with competitors from as far afield as Reunion Island and the USA compete to complete the 32-mile race across the rugged Northern section of the Kintyre Way.
Sixteen employees of main race sponsor SSE took part in the event, with eight running either the full course or as part of a relay team and the remaining eight volunteering as route marshals, finish line marshals and providing transport for bags and runners in their support vans.
This year’s challenging 52km route began with a sandy start north out of Tayinloan before beginning an ascent across the Kintyre peninsula at Clachan, descending into Skipness on the east coast before again climbing over the uplands, finally terminating in sun-drenched Tarbert along the quayside of the picturesque harbour.
SSE’s two relay teams embraced the challenge and ran with it, with Seagreen Supersonics - consisting of Martha Lovatt, Bruce Henry and Mark Timmons - taking first place and The SSE Second’s (Mike Blair, Craig Cunningham, Derek Belford) living up to their name and claiming second spot.
The volunteers from SSE gave up their time as part of company’s Be The Difference scheme which allows employees to give up one of their working days to volunteer at benevolent events within the community
Race organiser Rob Reid said:
“Among the 150 trail-runners taking part this year were eight from SSE but an event like this also depends heavily on volunteer helpers for tasks like driving support vans, staffing water stations, supervising road crossings, and general marshalling and SSE came up with an enthusiastic band of volunteers.
“To sum up, SSE really entered into the spirit of the event.”
Male Ultra Podium:
1st - Paul Monaghan (04:21:54)
2nd - Duncan Steen (04:23:39)
3rd - Willy Mamy (04:37:38)
Female Ultra Podium:
1st - Elaine Somerville (05:21:59)
2nd - Katharine Sims (05:32:57)
3rd - Elly Gaunt (05:51:18)
Relay Podium:
1st - Seagreen Supersonics (SSE) - 04:52:10
2nd - The SSE Seconds - 05:11:24
3rd - Thompson Twins - 05:28:00

ENDS
SSE RENEWABLES TEAM UP WITH CIRCULAR ECONOMY CHAMPIONS
07 May 2019
Award-winning local innovators Renewable Parts Ltd have joined forces with SSE to explore how adopting a circular economy approach can boost the renewable developer’s green credentials even further.
SSE’s ambitions to replace Tangy’s 22 older turbines with 16 more efficient, modern machines creates an opportunity for the old turbine components to be refurbished locally in Lochgilphead and even reused at other wind farms around the world.
In consultation with SSE Renewables, Renewable Parts Ltd is developing capability to decommission turbines to maximise the potential for re-use of component parts. The existing Tangy operation provides one of the first opportunities to decommission a UK wind turbine site responsibly by minimising waste and making the most of our resources, key principles of the circular economy
Refurbishing parts would minimise the amount of materials which may otherwise be scrapped, therefore helping to further reduce Tangy’s carbon footprint. The Scottish Government considers the next key issue for onshore wind is that of repowering and that the sector should do more to secure such supply chain and wider economic benefits.
A visit to the Lochgilphead refurbishment centre - itself a refurbished ambulance station - allowed SSE Renewables to explore how both companies can help improve the environment and local economy, whilst spearheading Scotland’s repowering industry in a responsible manner.
Renewable Parts’ Technical Director Ewan Anderson said: “As an Argyll based business, specialising in the wind turbine industry, we consider developments of this nature critical to the local economy, skills and jobs.
“Scotland is a world leader in wind power, pioneering many new wind turbine technologies. Our position at the forefront of one the UK’s leading sectors demands continued investment in state-of-the-art turbines. The proposed Tangy IV project represents a great opportunity to strengthen that position.”

ENDS
TANGY HELPS MCCORKINDALE TAKE TWO
30 April 2019
For over 40 years the McCorkindale School of Dance has been teaching the youth of Kintyre highland dancing.
Run by James McCorkindale, the dance school recently received a prestigious invitation to compete in the North American Highland Dance Championships, Las Vegas.
However, with a dance school filled with over 40 talented young dancers, James wanted to ensure that everyone had the chance to compete, whether across the pond or closer to home.
The Forth Bridges competition in Dunfermline was the perfect opportunity for members of the school to compete closer to home. However, two competitions mean twice the amount of funding to ensure these talented dancers get a chance to compete amongst their peers – and that is where Tangy wind farm comes in.
Whilst friends and family are continuously fundraising within the local community, the Tangy project team thought that some additional funding would help to ensure the competitions could be attended by as many members as possible.
James said: “It’s so important to ensure that every member of our dance group has the opportunity to compete in one of these wonderful competitions, so it was great to hear that SSE Renewables was happy to help support us.
“Competitions like the North American Highland Dance Championships and the Forth Bridges Competition are amazing experiences for the school and we are so grateful to all of our local supporters and projects like SSE Renewables’ Tangy wind farm for their help raising some much-needed funds.”

ENDS
POWERING THE KINTYRE WAY ULTRA 2019
26 March 2019
For the second year running, leading renewables developer, SSE, will be taking part in the Kintyre Way Ultra 2019.
Running is just one of the things SSE, owners of Tangy wind farm in the Kintyre peninsula, will be doing to support of this fantastic event. SSE will be powering the very people taking part in the event by contributing towards the sponsorship.
Seventeen members of the Tangy wind farm team will be either volunteering to help participants find their way along the route or taking on the gruelling endurance challenge, running the 32-mile track on the northern part of the Kintyre Way, beginning at Tayinloan and finishing at Tarbert.
For SSE, sponsoring the catering, goody bags and t-shirts was a no brainer. As Project Manager Andy Gregory explains:
“This community has been so supportive of us over the years and we are so pleased to have a chance to give back to them by helping with an event so close to the communities heart. We had a great time helping and taking part last year so we’re thrilled to be back again this year.
“I guess you could even say that it’s fitting we’re providing the catering on the day, after all, our Tangy wind farm has been providing energy for over 15 years and now we’re able to provide some much needed energy to the competitors on the day as they take on this tremendous race.
“On behalf of SSE and the Tangy wind farm team – good luck!”

ENDS
KINTYRE-BUILT TOWERS SET SAIL FOR SCOTLAND'S LARGEST OFFSHORE WIND FARM
13 November 2018
Six locally manufactured offshore wind turbine tower sections will depart from Campbeltown harbour this week on a two-day voyage to the SSE-led Beatrice offshore wind farm development.
The 6 metre diameter steel tower sections will form part of the Beatrice offshore wind farm off the Caithness coast, the largest private investment in Scotland.
The two complete towers shipped out this week are the first of a batch of six to be delivered during November, completing the order for 12 towers from CS Wind UK’s purpose-built manufacturing facility at Machrihanish and will be assembled at Nigg before being installed 13km offshore.
Lesley Black, UK Sales Team Leader at CS Wind UK said: “As a large local employer, these orders help reinforce vital job security to over 100 CS Wind UK employees, together with the local supply chain. Recent investment allowing fabrication of larger diameter offshore towers has enhanced our productivity and ability to meet the demand.”
The development and construction of Beatrice is being led by SSE, who will also operate the 84-turbine offshore wind farm once it is completed in spring 2019.
SSE are also seeking consent to re-power Tangy wind farm located north of Machrihanish. The project, known as ‘Tangy IV’ has stated an intention to procure the new turbine tower sections from CS Wind Ltd who have previously supplied towers for over a dozen SSE wind farms.
Jon Soal, SSE’s Project Manager for Tangy, said: “Tangy has been an exceptional site for SSE. The support we have received from the community over the past 15 years has been fantastic and is hugely appreciated by the project team.
“If consented, we hope that Tangy IV is able to build on the success of the original Tangy site and bring benefits to the local businesses and communities alike both during construction and throughout the lifetime of the project.”

Pictured above: Machrihanish-built turbine tower sections destined for Beatrice offshore wind farm in the Moray Firth. Credit - Raymond Hosie.
ENDS
CAMPBELTOWN BRASS BLOWS WITH THE WIND
03 October 2018
Campbeltown Brass received a welcome gift from SSE’s Tangy wind farm with some much-needed funds to help get the band to the National Brass Band Championships.
With the event hosted in Cheltenham, the trip of epic proportions meant a bus journey of over twelve hours, around 466 miles from the band’s hometown, and also overnight accommodation, rehearsal space and other expenses, all of which proved a significant challenge for the band.
However, thanks to lots of hard work from the band members, supporters and other donations, including a generous donation from Tangy wind farm towards the overall costs, the band were able to make the lengthy journey and compete in this fantastic event.
Jon Soal, SSE’s Project Manager said: “Campbeltown Brass is a really successful community organisation at the heart of the local community and we are very proud to be able to help them.”
“With the operational Tangy wind farm and our current redevelopment proposals, we have been working in the local community for a long time, so when we heard that the band might struggle to get to the championships we wanted to do something to help them get there to experience such a great event.”
The National Championships is the most prestigious brass band competition in the world, running since 1945. The final stage in the competition is only open to those who qualify at the regional championships across the UK. As current second section champions, Campbeltown Brass qualified to attend the competition as one of the final 18 qualifying brass bands. The chance to compete in this prestigious music event is a fantastic experience for young musicians and offers bands the opportunity to play with the best in their section from across Britain.
Katrina Barr of Campbeltown Brass said: “The band are extremely grateful to SSE for the donation and it really made a huge difference to our fundraising efforts.”

Pictured above: SSE’s Tangy wind farm gifts a donation to Campbeltown Brass for their trip to the National Brass Band Championships in Cheltenham.
ENDS
TANGY WIND FARM LOOKS FORWARD TO A NEW CHAPTER OF ITS RENEWABLE STORY
20 September 2018
The Kintyre peninsula looks set to receive a boost to its renewable credentials thanks to the submission of a new Tangy redevelopment application, with the potential to bring opportunities for local people and businesses alike.
For over 15 years, SSE’s Tangy wind farm, situated on the Kintyre peninsula, has been generating renewable energy and providing employment. Last week, SSE submitted a Section 36 application for Tangy IV wind farm, a redevelopment of the existing Tangy site.
The redevelopment proposals include removing the existing 22 turbines and replacing them with 16 of the latest modern turbines which could see the total installed generating capacity increase from 18.7MW up to around 80MW.
The proposals have optimised the previously consented Tangy III project, taking advantage of developments in wind turbine technology to maximise output from the site and contribute to the Scottish Government’s ambitious renewable energy targets.
As a responsible developer and operator of onshore wind, SSE is committed to ensuring as many local businesses and people as possible benefit from the opportunities our wind farm developments bring with them and plans to utilise as much of the existing site infrastructure as possible to minimise any local impact.
During construction and throughout its long-term operation, Tangy IV is anticipated to bring significant local opportunities including; direct local employment on site and within the supply chain, local provision of supplies, materials and plant; increased spend in local shops and businesses from the project and provision of local accommodation for those visiting or working on the site from further afield.
If consented, SSE would aim to ensure as many opportunities as possible are available locally and would hold a ‘meet the buyer’ event prior to construction so that local businesses can meet with SSE and its contractors and see how they might get involved. As one of the UK’s biggest Living Wage employers, SSE guarantees those working on the project are paid fairly whether for SSE directly or across our supply chain.
As an important local employer, with around 130 employees, it is SSE’s intention to procure the turbine tower sections from CS Wind Ltd based in Machrihanish, who have previously supplied towers for over a dozen SSE wind farms.
Jon Soal, SSE’s Project Manager, said: “Tangy has been an exceptional site for SSE. The support we have received from the community over the past 15 years has been fantastic and is hugely appreciated by the project team.
“If consented, we hope that Tangy IV is able to build on the success of the Tangy site and bring benefits to the local businesses and communities alike both during construction and throughout the lifetime of the project.”
ENDS
PUBLIC EXHIBITIONS
20 July 2018
SSE Generation is holding public exhibition events in relation to the proposed Tangy IV Wind Farm proposals.
We would like to extend an open invitation to these exhibitions to provide local communities and interested parties the opportunity to come along and meet with the project team, learn more about the project and raise any questions or concerts.
ENDS
TANGY TEAM POWER THROUGH THE ULTRA
16 May 2018
On Saturday 5 May, 19 members of SSE’s Tangy wind farm team arrived in Kintyre to run, cycle and support the Kintyre Way Ultra.
The Tangy site has been generating renewable energy for around 15 years, but 2018 was the first year the Tangy team came together to take on the Kintyre Way Ultra. In total, they covered nearly 500 miles to help raise money for their chosen charities.
Completing the Ultra on foot or on two wheels is a huge achievement for anyone, but for Tangy’s Project Manager, Jon Soal, who took on the Ultra Cycle, it also provided a chance to see the area from a different side.
Jon said: “I’ve been through to Kintyre on numerous occasions over the years but I have never had a chance to experience it in this way. It was definitely hard going completing the Ultra Cycle but it was worth it, fingers crossed I will make it back again next year!”
Six members of the team were also on hand throughout the day to offer organisers and competitors support, from keeping moral up to driving support vehicles back and forth on the day.
One member of the team, local resident and SSE’s Wind Operations Supervisor, Craig Scally, was in charge of one of the SSE support vehicles.
Craig said: “The Kintyre Way Ultra is a fantastic event to be part of, whether you’re racing or helping to keep the race going.
“I’ve been working on Tangy for 13 years now and it’s great to have been able to give back to the community by supporting this spectacular event. Although I must admit, it was a bit easier driving it than running it!”

ENDS
TANGY PROJECT TEAM TAKE ON KINTYRE WAY ULTRA
25 April 2018
The Tangy wind farm project team, from renewable energy developer SSE, will be looking to make 13 their lucky number as a group of 13 employees tackle the Kintyre Way Ultra on 5 May.
With spectacular views along the coast from Tarbert to Campbeltown the team will be taking in the breath-taking sites as they take on the Ultra on foot and on two wheels.
An additional six members of the team will be on hand to help out on the day and cheer on the runners and cyclists as they take on the gruelling endurance task.
Michael Blair, a Senior Analyst in SSE’s generation business, is taking on the Ultra solo which will see him run 35.5miles. Michael will be running for MND Scotland, the only Scottish charity that supports people affected by Motor Neuron Disease, as well as funding vital research to find a cure, you can sponsor Mike.
Taking on not just a marathon, but an ultra-marathon, isn’t for everyone, but Michael is taking it in his stride. Michael said: “I figure events like this are more about determination than fitness – at least I hope so! I’m just going to take my time, try and enjoy myself and remember that I am doing this for a very worthy cause.”
Another member of the SSE team tackling the Kintyre Way Ultra, but on two wheels is, Jon Soal, the project manager of SSE’s Tangy wind farm. Jon, along with a number of members of the SSE team, is taking on the challenge to raise money for BEAT, the UK's eating disorder charity, with a vision to end the pain and suffering caused by eating disorders.
Two years ago a member of SSE’s renewables team lost his daughter after a lengthy battle with bulimia. Now the team is working hard to raise money and awareness of this often-misunderstood mental illness.
Jon said: “It’s amazing to be able to take part in something that is for a truly great cause. Our whole team want to support our colleague and help them raise awareness of eating disorders in the hopes that one day no one will suffer the pain that their family went through.”
“I’m a keen cyclist and I am always looking for a challenge to take on - this Ultra Cycle seemed perfect. Working on Tangy I’ve visited this area a number of times but I never experienced it in this way, I’m really looking forward to it.”
Good luck to everyone taking part on the day.
ENDS
Contact info
If you have any queries or wish to speak with the project team, please contact:
Pauline Allison - Stakeholder Engagement Manager
Email: pauline.allison@sse.com
