Tangy Repower

In 2019, SSE Renewables was granted consent by Scottish Ministers to construct and operate Tangy IV (Tangy Repower), a 16 turbine wind farm with turbines up to 149.9 metres in height. The project would replace the existing 22 turbine Tangy Wind Farm, located approximately 9km northwest of Campbeltown on the west coast of the Kintyre Peninsula in Argyll & Bute.

However, the project which received consent is no longer deliverable in its current form, for two related reasons. First, turbines of the consented blade tip height of 149.9m are effectively no longer available on the market. The onshore wind turbine market has moved towards larger, more efficient machines, and manufacturers are increasingly phasing out turbines of the smaller dimensions consented in 2019. A variation to increase the consented tip height is therefore needed to enable a turbine that is available to be procured and installed. Second, the consented scheme is no longer commercially viable in its current form, principally due to rising supply chain costs and high transmission charges affecting the onshore wind sector in Scotland. The taller, more efficient turbines proposed both restore the commercial viability of the project and allow a currently available turbine model to be procured.

To raise awareness of the application and provide details of where hard copies can be viewed etc., a Public Notice was placed in local and national newspapers. A copy of the notice is shared below:-

Tangy S36C - Public Notice 2026

Number of consented turbines
Potential generating capacity up to
MW

Section 36C Variation Application

Thank you to everyone who attended our public exhibitions in August 2025 and March 2026. It was great to meet local residents and interested parties, discuss our plans, and answer questions.

Feedback from these events, alongside input from statutory consultees, environmental surveys and technical assessments, has helped inform our Section 36C Variation Application to the Energy Consents Unit.

You can view all the Application documents in the links below.  Links for the 2018 consented application (Tangy IV S36) are also below should you wish to re-visit them.

Decommissioning Tangy

The existing Tangy Wind Farm consists of two developments (Tangy I and Tangy II) with a combined installed capacity of 18.7MW. Tangy I comprises 15 turbines, and Tangy II comprises 7 turbines.

If consent is granted for the variation to Tangy Repower, the existing 22 turbines — some of which have been operating since 2003 — will be removed and replaced with 16 modern, more efficient turbines. Advances in turbine design mean the site could generate significantly more electricity, with a potential increase in capacity from 18.7MW to up to 96MW.

We have applied to Argyll and Bute Council, in July 2026,  seeking approval for an extension to the operational life of Tangy I and Tangy II wind farms until 2032. If approved this will enable the existing wind farms to continue operating while Scottish Ministers consider our application to vary the S.36 consent for the repowering of the Tangy IV Wind Farm.

Important documents

Tangy IV S36C Variation

Tangy IV S36C Variation - project redesign

Tangy IV S36

Tangy I S42

Tangy II S42

News and views

Contact info

If you have any queries or wish to speak with the project team, please contact:

Pauline Allison - Stakeholder Engagement Manager

Email: pauline.allison@sse.com