Tangy Repower

In 2019, SSE Renewables was granted consent by Scottish Ministers to construct and operate Tangy IV (Tangy Repower), a 16-turbine Wind Farm, which will replace the existing Tangy Wind Farm situated approximately 9km northwest of Campbeltown on the west coast of the Kintyre Peninsula in Argyll & Bute.

 

Following careful consideration and a detailed project feasibility review, SSE Renewables submitted a revised Scoping Report for Tangy IV (Tangy Repower) in July 2025. 

 

Since the project’s consent in 2019, our project team has been working to progress the project towards construction. However, due to a range of economic challenges and technological advances, it will not be possible to progress the project in its current form. We are therefore seeking to amend the 2019 consent to allow for the turbines on site to have an increased tip height of up to 200 meters.

Number of consented turbines
Potential generating capacity up to
MW

Tangy I & Tangy II had consent to operate until August 2022. SSE Renewables sought permission to extend the operational period to coincide with the planned end of the construction phase of Tangy IV.

A Section 42 Planning Application including Environmental Impact Assessment was therefore submitted to Argyll and Bute Council requesting an extension to the operational period. This was granted, allowing the existing wind farm to continue generating power until the end of 2026.

Next steps

SSE Renewables invites you to attend one of our public consultation events to view and share feedback on our project re-design proposals for the consented Tangy Repower project.

Since the project’s consent in 2019, our project team has been working to progress the project towards construction. However, due to a range of economic challenges and technological advances, it will not be possible to progress the project in its current form.

Our project team will be on hand to answer any questions on each day, with all feedback shared at the events helping to inform the submission of a Section 36C Variation application to the Scottish Government’s Energy Consents Unit (ECU).

Event details

Event 1:

Campbeltown Town Hall
Tuesday 26 August 
16:00 - 19:00                           
54 Main Street, Campbeltown, PA28 6AB         

Event 2:

Machrihanish Village Hall
Wednesday 27 August
11:00 - 14:00                                          
Bayview, Machrihanish, PA28

Event 3:

Tayinloan Village Hall
Wednesday 27 August
16:00 - 19:00         
Tarbert Road, Tayinloan, PA29 6XG

Decommissioning Tangy

The existing operational Tangy Wind Farm comprises two developments (Tangy I and Tangy II) delivering an installed capacity of 18.7MW. Tangy I has 15 turbines, and Tangy II has 7 turbines.

Tangy IV will include removing the existing 22 turbines, some of which have been generating since 2003, and replacing them with 16 more efficient modern turbines. Taking advantage of the advances in wind turbine design and technology will maximise output from the site and could see the installed site generating capacity increase from 18.7MW, potentially up to 96MW.

Tangy I & Tangy II had consent to operate until August 2022. SSE Renewables sought permission to extend the operational period to coincide with the planned end of the construction phase of Tangy IV.

A Section 42 Planning Application, including Environmental Impact Assessment, was therefore submitted to Argyll and Bute Council requesting an extension to the operational period. This was granted, allowing the existing wind farm to continue to generate up until the end of 2026.

A further planning application to extend the life of the site again is anticipated due to changes in the programme. More information on this will follow in due course.

Important documents

Tangy IV S36C variation - project redesign

Tangy IV S36

Tangy I S42

Tangy II S42

News and views

Contact info

If you have any queries or wish to speak with the project team, please contact:

Pauline Allison - Stakeholder Engagement Manager

Email: [email protected]