Back to overview

GE’s Haliade-X 14MW turbine to debut at third phase of Dogger Bank

18 Dec 2020

18 December 2020: Dogger Bank Wind Farm and GE Renewable Energy have today confirmed GE as preferred turbine supplier for Dogger Bank C, announcing at the same time plans to pioneer the upscaled 14MW Haliade-X turbine for this phase.

The 14MW Haliade-X is an upscaled version of the 13MW Haliade-X, the most powerful turbine in operation today, and installation at Dogger Bank C will mark the first time these turbines will be installed at any project world-wide.

The Turbine Supply Agreement and Service and Warranty Agreements for Dogger Bank C will be finalised in the first quarter of 2021, confirming the order and number of turbines and marking continued progress in the delivery of the third phase of the wind farm. These agreements will be subject to Dogger Bank C, which is a joint venture between SSE Renewables and Equinor, reaching Financial Close in late 2021.

Installation of the turbines for Dogger Bank C is set to begin in 2025 ahead of completion of the overall project in 2026.

At 3.6GW Dogger Bank will be the largest wind farm in the world, capable of generating enough renewable power to provide around 5% of the UK’s electricity demand. It is being built in three 1.2GW phases; Dogger Bank A, B and C.

GE is now confirmed as supplying Haliade-X turbine technology to all three phases of Dogger Bank Wind Farm including a record-breaking order for 190 units of GE’s 13MW Haliade-X for phases A and B.

Steve Wilson, Dogger Bank Wind Farm’s Project Director at SSE Renewables, said: “We’re delighted to be working with GE Renewable Energy on all three phases of our development, as the first wind farm in the world to install their innovative and record-breaking Haliade-X turbine technology. Together with GE we are continuing to lead the way on innovation in the offshore wind industry and we’re proud that Dogger Bank will now use a 14MW turbine at Dogger Bank C alongside the 13MW turbine already confirmed for phases A and B.”

John Lavelle, President & CEO, Offshore Wind at GE Renewable Energy, said: “Dogger Bank C will use a 14MW version of the Haliade-X, the most powerful offshore wind turbine in operation today. In doing so, this unique project will both continue to build on the UK's leadership in offshore wind and serve as a showcase for innovative technology that is helping to provide more clean, renewable energy.”

Halfdan Brustad, vice president for Dogger Bank at Equinor, said: “Once again, GE has demonstrated competitiveness with its ground-breaking Haliade-X, and we are delighted we will be working with them across all three phases of Dogger Bank Wind Farm. Turbine innovation has played a huge role in bringing down the cost of offshore wind, and these world-leading turbines will help us deliver renewable electricity at the lowest cost possible for millions of people across the UK. With our partner SSE Renewables, we are pioneering new technology whilst delivering a project that will create hundreds of skilled jobs. As operator for the project, we look forward to working with the GE team for many years to come.”

Located over 130 km off the north east coast of England, each phase of Dogger Bank Wind Farm will be able to produce 6TWh of renewable electricity, totalling 18TWh annually, equivalent to powering six million UK homes each year.