Greater Gabbard Extension

In October 2018 Greater Gabbard Extension successfully applied for The Crown Estate’s offshore wind farm extension process.

In August 2019 Greater Gabbard Extension successfully passed its Habitats Regulation Assessment and was awarded seabed rights.

The project will now proceed to make a DCO application in due course.

About Greater Gabbard Extension wind farm
LocationOff the East Coast of England
Ownership50:50 SSE Renewables and innogy
Proposed MW capacityUp to 504MW
StatusScoping